HEX Consultancy · Demo Project Dashboard

2 Basement + 12 Floor Tower — Progress & Cost Dashboard

Every figure across these tabs rolls up from the editable activity database (Cost-Loaded Schedule tab) — change a cost or a % complete there (or use the quick what-if) and every tab recalculates.

Data date: Jun ’26 · Month 10 of 24
Standalone
📋

Computing summary…

Cumulative progress: planned vs. earned

Cost-weighted baseline (S-curve) vs. actual earned value. The horizontal gap between the two markers at the data date is the schedule slip.

Planned (baseline) Earned (actual) Data date / slip

Cumulative budget: planned vs. real

Planned cumulative budgeted cost (Cost-Loaded Schedule) vs. real cumulative incurred cost (Actual cost ledger) — the gap between the two is cash spent faster or slower than budgeted, independent of physical progress.

Planned (budgeted cost) Real (incurred cost) Current reporting month

Assumptions & quick what-if

Actual cost isn’t in the activity database (it’s project-level, not per-task) — set it here. Use the slider for a fast scenario; edit the database below for real, task-by-task updates.

$
Variation orders approved
0
Value added to contract
$0
Cost added to budget
$0
$
Typing a new total rescales every activity's budget proportionally to hit it. For a non-uniform change, edit a single activity's budget in the Cost-Loaded Schedule tab instead. This field is the activity-database sum only — the Budgeted cost shown elsewhere on this dashboard (KPI row, Financial snapshot, Profitability) also adds approved variation order cost from the card below.
$
Driven by the Cost Ledger (Monthly Report tab) once anything's logged there — document each incurred cost as it comes in rather than typing a figure here directly.
Quick what-if: overall physical progress45%
Data date — fast-forward previewJun’26 · Month 10
Today reported · M1Full completion · M24
Schedule slip forecast—
3 mo aheadOn schedule6 mo critical

Site snapshots placeholders

No real site photos are attached to this demo — these are illustrative placeholders by phase. Attach real progress photos here once available.

Delay & risk flags

Auto-generated from the database below — whatever you edit there, this list (and its severity) updates with it.

Change orders & variations —

Starts empty — log real variation orders as they're raised. Once a row's Client decision is set to Approved, its billed value flows into the Contract value box above, and its actual cost flows into the Budgeted cost (BAC) used in the KPI row, Financial snapshot and Profitability panel — leave actual cost blank/$0 until you know it, so this change order doesn't silently show 100% margin. Set it back to Pending or Rejected at any time to remove it from both totals again. PM status (Proposed/Withdrawn) is separate and never affects these totals — it's your own record of whether you still stand behind the VO. Every status change is recorded — open a row's Docs button to see its full history.

Cost vs. contract value

Budget (cost) vs. selling price, and where forecast cost performance is pushing profit.

Profitability

Prorata assumption (as requested) alongside a cost-performance-based forecast.

Financial snapshot

Cash flow & payment certificates —

The question a client PM usually asks first: how much cash has actually moved, not how much work is theoretically earned. Starts empty — log each period's real certified receipt and real subcontractor/supplier payments below.

Cash flow forecast — through —

The single number an owner actually loses sleep over: how much cash is needed, and when — not just how much work is theoretically earned.

Project modality of payment

Payment certificate —

Client payments & overdue receivables

Record each receipt from the client against its certificate (full or partial). Kept separate from the monthly Cash flow log above, so nothing is counted twice.

+ Add an earlier certificate (issued before this register existed, or imported months)

Record a receipt

Financial billing milestones

Each certificate is tied to specific activities finishing — certify them in the database below and billing status here updates automatically.

HEX Consultancy · 2B+12F Tower demo dashboard · report generated .